South African Bulk Terminals
Executive Intelligence · Q3 2026

Command Dashboard

A forward-looking, decision-first view of terminal performance. Every figure is traceable to source and can be interrogated in plain language.

Board Intelligence Brief · Q3 2026

The quarter was shaped by three converging pressures: a legacy-asset failure, a product-quality event, and vessel scheduling breakdown — each with a traceable cost trail.

3Critical
4Watch
1On Target

Priority indicators

Ordered for the CEO view

Vessels Handled
Amber
1710.5%
Target 20Prev Q 19
Dispatched Tonnage
Amber
299 606 MT3.7%
Target 320 000 MTPrev Q 311 250 MT
Discharged Tonnage
Green
344 482,91 MT8.0%
Target 330 000 MTPrev Q 318 900 MT
On-Time Arrivals
Red
2%94.1%
Target 75%Prev Q 34%
Mechanical Downtime
Red
177 hrs84.4%
Target 80 hrsPrev Q 96 hrs

Old SKT bogie derailment = 120 hrs (~68%)

Overtime Hours
Red
17 874,16 hrs25.9%
Target 12 000 hrsPrev Q 14 200 hrs

Mid-week portion 1,874.47 hrs (~10%)

On-Time Departures
Red
20%51.2%
Target 75%Prev Q 41%
Mechanical Breakdowns
Amber
712.5%
Target 6Prev Q 8

What needs a decision

Computed from severity x business impact, not a static list

Management Attention Board

Auto-computed

Priority derived from each item's RAG status × business impact — not a hand-maintained list.

CriticalRice/sunflower contaminationnew

~11,000 MT rice contaminated with sunflower seeds; extensive cleaning and commercial exposure.

OperationsOwner: J. van WykRaised: 2026-08-14
CriticalOld SKT bogie derailmentresolved

Derailment caused 120 hrs downtime (~68% of quarter total) with cascading discharge and vessel delays.

Mechanical Eng.Owner: M. NdlovuRaised: 2026-07-11
CriticalLow on-time vessel performancerecurring

On-time arrivals 2% / departures 20%. Driven by rain, plant issues and silo bottleneck.

ShippingOwner: D. MokoenaRaised: 2026-08-18
HighOvertime hours escalationrecurring

17,874 hrs overtime, driven by downtime recovery and absence backfill.

PeopleOwner: L. DubeRaised: 2026-08-20
HighAging fibre infrastructurerecurring

Legacy fibre poses availability risk to terminal networks.

TechnologyOwner: T. PillayRaised: 2026-07-30
HighLegacy SCADA systemsrecurring

Outdated SCADA increases operational and cyber risk on control systems.

TechnologyOwner: M. NdlovuRaised: 2026-07-30

Early-warning radar

Trajectory projected from weekly signals before thresholds breach

Early Warnings

Predictive — separate from current-state attention board
Unplanned Absence
Rising 1.4 %/wk
Red in ~3 wks

Projected to cross the Red threshold (38%) in ~3 weeks at the current trajectory.

Cross-department patterns

Connections a single-department report would miss

Pattern Recognition

Auto-generated insights, each grounded in the dataset

Absence concentrates on Mondays & Fridays

Amber

Unplanned absence is heavily skewed to the start and end of the week — Mondays and Fridays account for 45.8% of all unplanned absence, a classic attendance-pattern signal worth a targeted policy response.

Confidence86%
Source: People → Absence analysis (1,242.9 leave units, 34.4% unplanned)

A single event drives most downtime

Red

Mechanical downtime is not broad-based: the Old SKT bogie derailment alone accounts for 120 of 177 hrs (~68%). Addressing legacy-line reliability would remove the bulk of the exposure.

Confidence94%
Source: Mechanical → Downtime breakdown (177 hrs total, 7 breakdowns)

Cyber remediation up, incidents flat at zero

Green

Vulnerabilities remediated rose to 6,320 (from 4,980) while major security incidents held at zero and the DR test passed — evidence the proactive posture is working.

Confidence90%
Source: Technology → Cyber (6,320 remediated, 0 incidents, DR passed)